People - Views and Filters

Last updated: November 13, 2026

People views and filters help you visualize and narrow down your workforce data in Bridgit. You can switch between List and Gantt views to see your team in different formats, then apply filters to focus on specific groups, availability, certifications, or any other criteria that matters to your planning.

Key capabilities:

  • Switch between List and Gantt views to match your workflow

  • Customize columns to show the data you need

  • Filter on system fields, custom fields, and certifications

  • Save filters that are frequently used for quick access

  • Apply Gantt-specific display options for visual planning

  • Change assignment dates by dragging assignments bars in the Gantt view

  • Send broadcast messages to filtered groups of people

  • Export filtered data to CSV, PDF, or Excel


Eligibility/Prerequisites

Access to People views and filters depends on your permission level:

  • View People: See and filter people data in both List and Gantt views

  • Edit People: Manage fields on profiles

  • Manage Broadcast: Send broadcast messages to people (requires appropriate permission level + the communication module)

  • Drag and drop assignment edits: Requires both Manage Assignments and Manage Roles for that profile type (salaried or hourly). Dragging an assignment past the project’s start or end date also requires Edit Project Dates. If you don’t have these permissions, you won’t see drag handles on project bars.

Your ability to see certain data may be restricted based on profile type permissions. If you only have permission to view salaried or hourly profiles, you'll only see data for that profile type.


How to Use

People List View

The List view displays your workforce in a table format with customizable columns.

Customizing Columns

  1. Click the Columns button in the top right beside the export button

  2. Select the columns you want to display

  3. Drag column headers to reorder them

  4. Your column selections remain sticky as you navigate Bridgit

Applying Filters

You have three ways to filter people:

  1. Add Filter button: Click Add Filter on the left to access all available fields, including those not currently displayed as columns. This is the most comprehensive filtering option. Apply one or multiple filters at a time.

  2. Quick filters: Use the dropdown buttons for filters such as Title and Availability for fast, common filters.

  3. Column-based filtering: Click the triangle icon on column headers to filter directly on that field.

Saved Filters

If you use a filter regularly, save it for quick access:

  1. Apply your desired filters

  2. Click Bookmark icon beside the applied filters

  3. Name your filter descriptively

  4. Access saved filters anytime from the Add Filter dropdown

Exporting Data

You can export your People table to CSV, PDF, or Excel by clicking the export icon in the toolbar above the table.

Broadcasting Messages

With appropriate permissions, you can send messages to people:

  1. Apply filters to identify your target group

  2. Click Send Broadcast (paper airplane icon - located in the top right, beside the export button)

  3. Compose your message

  4. Send to all people in your filtered view


People Gantt View

The Gantt view provides a visual timeline of workforce allocations and availability.

Understanding the Display

The People Gantt shows two types of bars for each person:

  1. Utilization bar (top of each row): Shows overall capacity with color coding:

  • Blue: Fully assigned (100%)

  • Green: Fully available (100%)

  • Light green: Partially available

  • Orange: Over-allocated (above 100%)

  • Black: Time off

  1. Project bars (below utilization): Show specific assignments on projects. Each project bar spans the duration of that assignment.

  • Solid bars: Awarded projects

  • Faded bars with dotted outline: Pursuit projects

  • Colors may vary based on your account's project color configuration

Gantt Display Options

Access Gantt Settings on the right-hand side (gear icon) to customize what you see:

Row content:

  • Projects & utilization: Show both bar types (default)

  • Projects: Show only project assignment bars

  • Utilization: Show only capacity bars

  • Enable Drag & Drop Interactions: Turn drag and drop editing of project bars on or off. On by default, and your choice is remembered. Only visible to users with permission to edit assignments.

Sort by:

  • Select any custom or system field to sort the data by

  • Add preferred sorting options for quicker access

Applying Filters in Gantt

All standard filters work in Gantt view:

  • Click Add Filter to filter on any field

  • Use quick filters for Title and Availability

  • Your filters persist when switching between List and Gantt views

Interacting with the Gantt

The Gantt is dynamic and interactive:

  • Drag project bars to change assignment dates (see Editing Assignments with Drag and Drop below)

  • Scroll horizontally across the timeline

  • Click profile pictures to open full people profiles

  • Click utilization bars to see and edit allocation details

  • Click project bars to open project profiles directly

  • Click the + button beside a person's name to add them to a new project

  • Adjust the timeline view using the zoom levels

  • Choose between a compact or standard row height

  • Access fullscreen mode to take up your whole screen

  • Resize the legend by dragging its edge to accommodate long names

Editing Assignments with Drag and Drop

You can change a person’s assignment dates directly from the People Gantt by dragging their project bars.

To change a start or end date:

  • Hover over the start or end of a project bar until the drag handle appears

  • Drag the edge to the new date and release

To shift an assignment to new dates:

  • Click and hold the middle of the project bar

  • Drag it to the new dates and release. The assignment keeps the same length.

What happens when you drag:

  • Shortening an assignment: Days you remove show as unfilled on the role.

  • Extending past the role’s dates: The role’s dates extend to fit the assignment.

  • Extending past the project’s dates: You’ll be asked to confirm the project date change. Requires Edit Project Dates.

  • Overlapping another person on the same role: You’ll be asked to confirm. The other person’s assignment is shortened where the dates overlap, or removed if your assignment covers it entirely.

  • Precon assignments: Dragging moves the whole task, including every role and person on it. You’ll be asked to confirm first.

  • Hire and termination dates: You can’t drag an assignment before a person’s hire date or after their termination date. The bar stops at that date.

  • Minimum length: An assignment can’t be shortened below 1 day. To remove someone from a role, click the project bar and select Unassign.

Things drag and drop doesn’t do:

  • Change allocation percentages (click the utilization bar to edit these)

  • Move an assignment from one person to another

  • Connect split assignment segments across a 0% gap

Exporting Data

To export your Gantt view, click the export icon in the toolbar above the Gantt. You can select the timeline, page orientation and print size for your PDF.


Common Workflows

Adjusting assignment dates during a staffing meeting: Open the People Gantt and filter to the team you’re reviewing. As changes are agreed, drag project bars to update dates on the spot. If a change affects another person, a Precon task, or project dates, review the confirmation before saving.

Finding available workers for next month: Filter Availability to "Available" (choose from full, or partial availability) and adjust the zoom level to focus on the upcoming month. Use Gantt view with utilization display to see capacity at a glance.

Identifying over-allocated staff: Apply filters to narrow your view, then use Gantt with utilization-only display. Look for orange bars indicating over-allocation. Click the bars to see conflicting assignments.

Sending certification renewal reminders: Filter on Certifications set to "Expiring Soon". Review the filtered list, then use broadcast messaging to notify affected employees.

Reviewing a specific team's workload: Apply Title filters to select the roles you want to review. Switch to Gantt view to see their project assignments across the timeline. Adjust to projects-only display to focus on assignments without utilization clutter.

Planning capacity for an upcoming project: Filter by the titles you need, set your timeline to the project dates, and use the utilization display to identify who has availability during that period.

Exporting team contact information: In the List view, filter to your desired group of people, customize columns to show contact details, then export for external use.

Exporting the team's assignments: In the List view, filter to the desired group of people and use Columns to add Current Project and/or Next Project. Export to CSV, PDF, or Excel. For PDF exports, enable the Include Assignments toggle.


Common Questions

Q: Why do my column selections disappear when I log back in?

Column customizations are sticky to your user profile and should persist. If they're resetting, try clearing your browser cache or contact Bridgit Support if the issue continues.

Q: Can I share saved filters with my team?

Yes, saved filters can be shared with users in your account by administrators. When creating a saved filter, simply select the option to share filter with all users in the account.

Q: What's the difference between Quick Filters and Add Filter?

Quick filters provide fast access to the most commonly used filters (Title, Availability). Add Filter gives you access to all available fields, including custom fields and certifications, even if those columns aren't currently displayed.

Q: Why don't I see the Gantt display options?

Click the gear icon in the top toolbar on the right to open the Gantt Settings.

Q: How do I export my filtered data?

Apply your desired filters, then click the export button in the top right. You can export to CSV, PDF, or Excel. The export will include only the data visible in your current filtered view and selected columns.

Q: What does "sticky" mean for my view customizations?

Sticky means your selections (columns, filters, Gantt settings) are saved to your user profile and will remain when you navigate to other parts of Bridgit and return to the People section.

Q: Can I filter on fields that aren't visible as columns?

Yes. Use the Add Filter button to access all available fields, regardless of whether they're displayed as columns in your current view.

Q: How is availability calculated?

Availability is calculated based on each person's assignment percentages on projects for a given period. If someone has been allocated 50% to one project for a given month, they are considered 50% available for that given month.

Q: How to filter on custom fields I've created?

All custom fields for a specific account will appear as options in the 'add filter' button, and are also able to be added as columns in the people list view.

Q: Can I add a person to a project from the people gantt view?

Yes. Hover over the name of the person you'd like to assign. A + button will appear. Click the + and select Add to Project.

Q: How can I quickly resolve an overallocation?

If a resource is placed on numerous projects causing an overallocation, from the people gantt view, navigate to the overallocation, click into the allocation bar and select Split Evenly. This will automatically adjust the resource's assignment percentages to be equal across all projects, totaling 100%. Adjustments can be made to individual assignment percentages if needed.

Q: Why can't I drag assignment bars?

Check that Enable Drag & Drop Interactions is on in Gantt Settings (gear icon). If you don’t see that option or the drag handles, you don’t have permission to edit assignments for that profile type.